Week commencing 17 October 

Stage 2

  • Tiling continued
  • Unit 4: 
    • hydrepoxy slab 
    • calculate levels and pour slopes for correct drainage 
  • Unit 7: 
    • epoxy primer 
    • bond breaker 
  • Unit 8: 
    • epoxy primer 
    • bond breaker 
  • Unit 42 finished steel posts and for balustrade
  • Unit 45 completed internal consequential damage 
  • Finish FC sheeting around terrace level to Units 21 & 30 
  • Completed suspended ceiling under Units 21 & 30 

In the week ahead

Stage 1

  • Render above skirting tiles on terrace level around Units 21 & 30 

Stage 2

  • Tiling to continue
  • Unit 1 remove window, install new flashings, reinstall window 
  • Unit 2 remove window, install new flashings, reinstall window 
  • Unit 4 final coat of hydrepoxy and water stop angle to be installed 
  • Unit 7: 
    • bandage over expansion joint 
    • membrane 
  • Unit 8: 
    • bandage over expansion joint 
    • membrane 
  • Unit 20 finish levelling to get falls to drain and hydrepoxy 
  • Unit 42 support for internal balustrade 
  • Plant room, estimate area coverage and order fire rated materials