Week commencing 22 August

  • Roof terrace demolition - Completed

  • Unit 809 corrosion spot remediation - Completed 

  • Stage 12 corrosion spot remediation - 80% completed

  • Stage 10 render patching completed

  • Stage 11 - Completed

  • Stage 13 - render spot marked out, measured and broken out 

  • Torch-on detailing on Eastern courtyard sliding door hobs - Commenced

  • Reinstalled 2 sliding doors at Units 208 and 211

  • Roof terrace BBQ removed, ready to form up and pour concrete hob 

  • Painters delayed due to weather 

In the week ahead

  • Start grinding roof terrace, finish detailing new door hobs at Eastern courtyards

  • Electrician to disconnect roof lighting and GPOs

  • Painting works at Aluminium Stage 2 and Stage 10

  • Rendering works to be completed on Stage 11 and Stage 12

  • Continue re-installing sliding doors at Eastern courtyards

  • Start forming and pouring fence plinths/ hobs at Eastern courtyards and for roof terrace BBQ