Week commencing 29 August

  • Commenced grinding roof terrace membrane, completed detailing new door hobs at Eastern courtyards 

  • Roof terrace lighting and GPO's 

  • Completed Aluminium Stage 2 

  • Render patching completed at Stage 11 and Stage 12 

  • Reinstalled all sliding door at Eastern courtyards

  • Roof terrace BBQ prepared for concrete plinth

  • Level 2 Northern and Western courtyards prepared to start grinding up membrane  

In the week ahead

  • Render patching to be completed at Stage 13 

  • Start rendering reinstalled door reveals 

  • Complete painting works in Stage 10, 11, and 12

  • Strip Stage 10, 11, and 12 

  • Install Stage 14 

  • Continue grinding and preparing roof terrace 

  • Pour concrete plinths on roof terrace for BBQ and service cables

  • Survey roof terrace concrete slab levels 

  • Change pergola fixing to stainless steel at Aluminium Stage 2