Week commencing 5 September 

  • Render patching completed at Stage 13, started door reveals at Eastern courtyards

  • Painting completed at the Northern facade (excluding level 8 )

  • Stage 10, 11, and 12 stripped, scaffolds removed from site 

  • Stage 14 installed 

  • Roof terrace grinding - 80% completed 

  • Poured concrete plinths at Unit 814 services 

  • Poured new door hobs in Units 203 and 204

  • Demolished Unit 107 robe to locate source of leak 

In the week ahead

  • Mark out and break out render at Stage 14

  • Render repairs to continue on Eastern courtyard door reveals 

  • Complete roof terrace preparation and start torch-on membrane

  • Clean out Level 2 Northern and Western courtyards to start grinding up old membrane 

  • Change pergola fixings at Aluminium Stage 2 

   **  Please click for Mud Map of stages