Week commencing 17 October 

  • Completed torch-on membrane at Level 2 Northern and Western courtyards and commenced detail works on door hobs and perimeter upturns 

  • Continued internal repairs to Level 2 sliding door reveals, sills and ceilings at Units 208 and 211

  • Water tested new roof terrace membrane - positive results 

  • Started set-out and preparation of new concrete plinths at roof terrace and Level 2 fence posts 

  • Re-installed all Level 2 Northern and Western courtyard sliding doors (except Unit 201 and 202)

  • Swing Stage 15 & 16 installed 

In the week ahead

  • Continue roof terrace and Level 2 perimeter detailing with liquid membrane bandage 

  • Water test Level 2 East, North and West courtyards (all prepared)

  • Mark-out, document and break-out render patches at Stage 15 & 16

  • Start patching Aluminium Stage 3, Stages 15 & 16 and Level 2 Northern and Western door reveals 

  • Pour concrete hobs for fence posts on roof terrace 

  • Start electrical cabling works on the roof terrace

  • Cut-out parapet wall section above car park entry to load up materials onto Level 2 

  • Continue internal repairs to Level 2 sliding door reveals, sills and ceilings at Unit 209

   **  Please click for Mud Map of stages