Week commencing 07 November

  • Delivered and set-up concrete pump to Roof Top

  • Commenced screeding on Roof Top

  • Set out screed heights on Level 2 East podium slab

  • Continued bathroom inspections and quotes from Megasealed

  • Electrician started fence light cabling works on Level 2 East podium slab

  • Continued at Stage 15 & 16 render patching and corrosion spot remediation 

In the week ahead

  • Complete Roof Top screeding

  • Install epoxy membrane to Roof Top screed

  • Set up pump and commence Level 2 East podium slab screeding

  • Electrician to complete Level 2 East and West fence lighting cabling

  • Complete Stage 15 & 16 render patch and corrosion spot remediation 

  • Commence painting on Stage 15 & 16 

  • Strip Aluminium Stage 3 scaffold and install Stage 4 - at Unit 811 and 812

  • Commence internal (drywall and sill) repairs at Level 2 units

  • Tile delivery