Week commencing 14 November

  • Completed Roof Top screeding and cleaned up area

  • Commenced installation of epoxy membrane to Roof Top screed

  • Set up pump and completed Level 2 East podium slab screeding

  • Electrician completed Level 2 East and West fence light cabling 

  • Completed render patches and corrosion spot remediation on Stages 15 & 16

  • All door reveals have been rendered on Level 2 East up to hoist

  • Completed painting on Stage 16

  • Striped Aluminium Stage 3 and installed Stage 4 (at units 811 and 812)

  • Commenced internal (drywall and sill) repairs for Level 2 Units

  • 600sqm tiles delivered and loaded out to Level 2

  • Replaced bolts at spiral stair cases to Roof Top at units 801, 806, 809 and 814

In the week ahead

  • Complete epoxy membrane to Roof Top screed

  • Load out tiles and adhesive to commence tiling on Roof Top

  • Finish screeding on Level 2 East up to hoist

  • Clean up Level 2 and commence epoxy membrane installation to screed

  • Set out for tile expansion joints at Roof Top and Level 2

  • Complete painting on Stage 15

  • Mark out and break out render patches on Aluminium Stage 4

  • Receive 2nd batch of tile delivery

  • Continue internal plasterboard repairs to Level 1 & 2 Units