Week commencing 28 November

  • Completed tiling, grouting, skirting to Roof Terrace
  • Installed drains on Roof Terrace
  • Loaded out materials for tiling on Level 2 Western podium slab
  • Received fence delivery for Roof 
  • Completed installation of epoxy membrane on Level 2, North and East
  • Commenced tiling on Level 2
  • Marked and broke out render patches and corrosion spots on Eastern facade curved blade wall and adjoining balconies
  • Commenced render repairs on Aluminium Stage 4 and blade wall 
  • Received 3rd and 4th tile delivery batches
  • Continued grinding back old waterproofing membrane at unit 810 and 707 balconies
  • Continued internal plasterboard repairs for Level 2 Units
  • Stripped Stage 15 & 16 swing stage and relocated to Western side storage area
  • Megasealed booked and to commence works to affected bathrooms

In the week ahead

  • Prepare Roof Top for fence installation
  • Complete render patch and corrosion spot repairs at Aluminium Stage 4
  • Continue repairs on Eastern facade curved blade wall and adjoining balconies
  • Complete installation of epoxy membrane to Level 2 Western podium slab up to hoist
  • Commence painting on Level 2 Eastern facade walls and Aluminium Stage 4
  • Complete internal plasterboard repairs for Level 1 and 2 Units
  • Continue tiling on Level 2 East
  • Strip Stage 15 & 16 swing stages and commence installation of Stage 17

   **  Please click for Mud Map of stages