Week commencing 16 January

  • Stripped Aluminium Scaffold Stage 4 and installed Aluminium Scaffold Stage 5
  • Marked and broke out render patches and corrosion spots on Aluminium Scaffold Stage 5
  • Broke out all render patches and corrosion spots on Stage 17
  • Painted Unit 802 and 103 balconies, Western blade wall, Unit 107 robe and commenced Roof Terrace
  • Stripped steel 'catwalk' scaffold at Unit 802 balcony and scaffold from Western blade wall, all scaffolding removed from site
  • Commenced preparation works at Unit 201 and 202 courtyards for new torch-on membrane with coving, pressure wash and priming
  • Installed aluminium water stop angles on new concrete hobs at Unit 210 and 202
  • Poured last Level 2 fence plinth 
  • Prepared substrate and water proofed Unit 707 and 810 balconies, and also the narrow concrete awning above Units 101, 102 & 103
  • Installed new carpet in Unit 107 robe and Unit 103 corridor

In the week ahead:

  • Abseilers to commence painting remaining areas on Western, Northern and Eastern facade
  • Complete new torch-on membrane to Unit 201 and 202 courtyards
  • Electrician to rough-in new fence cablings
  • Tiling to Roof Terrace plinth tops, complete Level 2 skirting up to unit 202 courtyard
  • Complete screeding to Unit 810 and 707 balconies, also to remaining Level 2 area 
  • Commence demolishing Unit 809 upper balcony 
  • Start render and corrosion spot repairs at Stage 17 and Aluminium Scaffold Stage 5
  • Install new robe cabinetry to Unit 107