Week Commencing 24 April

  • Unit 6 and 7 balcony brick work and flashing's.
  • Unit 7 bathroom plastered.
  • Unit 7 sun-room inspection from triaxial.
  • Unit 7 HB40 repair (sun-room).
  • Render work to underside of slab and slab edges.
  • Unit 4 render works in bedroom.
  • Brick work acid wash.
  • Unit 4 break out in dining room (more spooling evident) plus mark up from engineer.
  • Unit 7 tile breakout.

In the weeks ahead

  • Unit 7 HB40 repairs (sun-room).
  • Unit 7 plaster sun-room.
  • Unit 7 painting bathroom and sun-room.
  • Unit 7 tile replacement.
  • Slab preparation for membrane (cut out thread rod from steel grids and treat, leveling where needed, hydropoxy).
  • Unit 4 spooling repairs and steel treatment.
  • Painting of render (boiler room underside slab).