Week commencing 24 October 

Stage 1

  • Render above skirting tiles on terrace level around Units 21 & 30 

Stage 2

  • Tiling to continue
  • Unit 1 remove window, install new flashings, reinstall window 
  • Unit 4 final coat of hydropoxy, bond breaker and install waterstop angle
  • Unit 7: 
    • bandage over expansion joint 
    • membrane 
    • UV stabiliser coating
  • Unit 8: 
    • bandage over expansion joint 
    • membrane 
    • UV stabiliser coating
  • Unit 20 finish levelling to get falls to drain and hydropoxy 
  • Unit 21 & 30 
    • FC sheeting and terrace level to be painted
    • caping on underside of fascia installed
    • Flood test Unit 30

In the week ahead

Stage 2

  • Tiling to continue
  • Unit 2 remove window install  new flashing, reinstall window
  • Units 7 & 8
    • lood test new membrane on balconies
    • reinstall decking, bearers and joists (new bearers and joists in Unit 8)
    • planter boxes to be fitted with core flute board, drainage cell, geo cloth and to be refilled with soil 
  • Unit 42 support for internal balustrade 
  • RFI: Plant room and fire rating
  • Final sand and paint of terrace suspended ceiling
  • Units 4 & 20 waterproof membrane 
  • Units 16, 17, 18 & 19 flood test and adjust spitters appropriately to drain into gutters