Week commencing 28 November 

Stage 2

  • Completed fire rating works to vent in plant room
  • Completed Block B planter's
  • Completed corrugated siding to Unit 25
  • Completed spitters to Unit 44 back balcony
  • Completed internal damage repairs to Unit 32
  • Painted Unit 42 bathroom ceiling 
  • Completed Unit 23 spitter (waterproof and tile)
  • Completed bedroom 2 flashing to window 
  • Established source of leak for Unit 23 dormer window 

In the week ahead

Stage 1

  • Complete tiling to Building A Stairwell 

Stage 2

  • Flood test, reinstate flashing, reinstate irrigation, install drainage cell and Geofabric Block B planter
  • Seek and follow further directed regarding water ingress to Unit 23
  • Remediate mould to Unit 39 ensuite
  • Replace carpet to wardrobe, Unit 43
  • Replace carpet to bedroom, Unit 39
  • Tile front balcony to Unit 44
  • Finish cladding and install last floor waste to Unit 25
  • Install whirly birds to Unit 43
  • 2x AC units to be mounted
  •