Week commencing 05 December 

Stage 2

  • Block B planter box
    • Completed flood test
    • Reinstated flashing, drainage cell and Geofabric
  • Completed direction of Unit 23 with corrugated foam installed above dormer window, and hose test
  • Mould inspection conducted in Unit 39 
  • Replaced Unit 43 wardrobe carpet 
  • Replaced Unit 39 bedroom carpet
  • Completed Unit 25 cladding and installed last floor waste
  • Installed Unit 43 whirly birds

In the week ahead

Stage 1

  • Complete tiling to Building A stairwell 
  • Building A decking repairs

Stage 2

  • Block B planter box
    • Complete irrigation
    • Refill soil
  • Seek and Follow further direction with water ingress to unit 23
  • Remediate mould in Unit 39 en suite
  • Tile Unit 44 front balcony 
  • Unit 28 down pipe works (providing access granted)
  • Clean Building B decking