Week commencing 14 November

  • Near completion of Unit 9 southern facade cavity flashing replacement
  • Near completion of Units 2 & 3 defect rectification (only drain detail remains)
  • Completion of Units 1, 4 & 6 defect rectification

In the week ahead

  • Finish cavity flashing replacement to Unit 9 facade
  • Rectify defects to Units 5, 7, 8 & 10
  • Detail drains to Units 2 & 3
  • Complete render works to Unit 9 southern facade