Week commencing 16 January

  • Unit 6 internal render removed.

  • Application of 1st and 2nd coat of CR-25 tanking membrane to Unit 6.

  • Removed Unit 6 tiles and topping.

  • 90% of tiles and topping removed from Unit 7.

  • Unit 5 landing demolition works started.

In the week ahead

  • Render Unit 6 internal.

  • Set up zip wall in Unit 7.

  • Remove internal render to Unit 7.

  • Apply 2 coats of tanking membrane to Unit 7 internal.

  • Remove internal render to Unit 5.

  • Apply 2 coats of tanking membrane to Unit 5 internal.

  • Finish unit 5 landing demolition works.

  • Close site Thursday & Friday.