Week commencing 23 January

  • Unit 6 internal render complete
  • Unit 5 landing demo near completion
  • Unit 5 internal render removed and ready to tank membrane
  • Unit 7 render removed and ready to tank membrane.

In the week ahead

  • Clean internal of unit 5
  • Tank Unit 5 & 7 internal
  • Finish external waterproof works Unit 6 & 7
  • Render internal Unit 5 & 7