Week commencing 30 January

  • Completed Unit 7 demolition works
  • 2 coats of hydropoxy to Unit 7 external membrane works
  • 2 coats of hydropoxy to Unit 6 external membrane works
  • 1st coat of eco-seal membrane and bandage bond breaker to Unit 6 external membrane works
  • Unit 7 internal tanking complete
  • Unit 5 internal tanking complete
  • Unit 7 internal render near completion
  • Unit 5 internal cleaning complete

In the week ahead

  • Finish internal render to Unit 7 
  • Finish internal render to Unit 5 
  • Commence Unit 7 internal paintings works 
  • Final coat of membrane to unit 6 external membrane works.
  • Apply 2 coats of membrane to Unit 7 external membrane works
  • Reinstate balustrade to Unit 6 and 7 boundary
  • Finish preparing Unit 5 landing/balcony slab for new membrane
  • Apply 2 coats of eco-seal membrane to unit 5 landing/balcony
  • Unit 7 external tiling works