Week commencing 06 February

  • Unit 7 render works complete
  • Unit 5 render works complete
  • Unit 7 internal paintings works complete
  • Final coat of membrane to unit 6 external membrane works
  • 2 coats of membrane to unit 7 external membrane works
  • Unit 5 balcony demolition complete

In the week ahead

  • Re-instate joinery item unit 7
  • Re-instate power outlets to units 5, 6, 7
  • Repair leaching in units 3, 6, 7, 8
  • Unit 6 and 7 external tiling works
  • Unit 5 internal skirting tiles
  • Detail tiles around unit 2 spa taps
  • Re-do verticle expansion joints
  • Install new termination angle to unit 5 balcony
  • Apply 2 coats of membrane to unit 5 balcony
  • Water test unit 5 balcony
  • Apply new LQ92 topping to unit 5 landing
  • Reinstate balustrades to unit 6 and 7
  • Over flash ecoseal membrane to unit 6 and 7 external rising damp works with wba 9000 membrane