Week commencing 13 February

  • Re-instated joinery item unit 7
  • Re-instated power outlets unit 5, 6, 7
  • Repair leaching unit 3 & 7
  • Bandage applied to unit 8 vertical control joint
  • New termination angle to unit 5 balcony installed
  • 3 coats of membrane and bandage bondbreaker to unit 5 balcony
  • New topping to unit 5 balcony landing 
  • Over flash ecoseal membrane to unit 6 and 7 external rising damp works with wba 9000 membrane
  • All tilling works on hold until unit 5 balcony is ready.

In the week ahead

  • Complete all tilling works
  • Install bandage to unit 6 and 7 vertical control joints
  • Repair leaching unit 6 & 8
  • Touch up coating and paint work where needed.
  • Install raven RP67 door hoods to units 6, 7, 8 
  • Re-instate balustrades unit 6 & 7