Week commencing 2 May 

  • Remove existing waterproofing and grind down drains in Block A
  • Treating the top side of the decking of Block B depending on the weather 
  • Putting in bearers and joists into unit 5& 6 and decking down
  • Completion of waterproofing removal around units 21 and 30. 

In the week ahead

  • Waterproofing removal in Block A to be completed
  • Reinstating the piers 
  • Forming the areas in Block A to create flow to drains 
  • Decking completed for balconies 5 & 6
  • Flood test storm water detention tank