Week commencing 9 May 

  • Waterproofing removal in Block A to be completed
  • Reinstating the piers 
  • Forming the areas in Block A to create flow to drains 
  • Decking completed for balconies 5 & 6
  • Flood test storm water detention tank

In the week ahead

  • Complete pier reinstatement
  • Forming the areas in Block A to create flow to drains will commence
  • The waterproofing removal process in Block A is to be completed earlier in the week
  • Follow up carpenters for return date for 5&6
  • Follow up crack injection
  • Follow up with location approval for
  • Follow up with roofers to see if they have submitted quote for further works and book in return date