Week commencing 16 May 

  • Complete pier reinstatement
  • Forming the areas in Block A to create flow to drains will commence
  • The waterproofing removal process in Block A is to be completed earlier in the week
  • Follow up carpenters for return date for 5&6
  • Follow up crack injection
  • Follow up with location approval for
  • Follow up with roofers to see if they have submitted quote for further works and book in return date

In the week ahead

  • Slopes on Block A to be completed
  • Balcony decking on 5 & 6 to be down
  • West end of Block A to be waterproofed
  • Scaffolds at the end of the week
  • Crack injection to start