Week commencing 23 May 

  • Slopes on Block A to be completed
  • Balcony decking on 5 & 6 to be down
  • West end of Block A to be waterproofed
  • Scaffolds at the end of the week
  • Crack injection to start

In the week ahead

  • Unit 5 & 6 staining to be completed 
  • Block A waterproofing to be completed 
  • Scaffoldings to go up for Unit 21 ans 30 terraces
  • Balustrade to come off in preparation for hobs to be installed
  • Core holed to be drilled