Week commencing 9 May

  • Complete swing stage move to the front of Units 03b and 04
  • Complete repairs to ensuite in 211
  • Complete inspection work in 211 bathroom and courtyard
  • Test, mark and document failing render on Western facade Units 04 and 03b and complete removal
  • Complete render repairs to Units 3a and commence painting work 

In the week ahead

  • Complete render repairs to stage 4 and stage 3 (excluding afs panels) prime patches
  • Test document prepare and repair stage 5
  • Engage CSS to begin installation of 4th stage 
  • Engage scaffolder for levels 7 and 8 on Western side
  • Phase 2 water test on unit 103
  • Gain access to unit 810 to begin balcony prep.