Week commencing 16 May

  • Complete render repairs to stage 4 and stage 3 (excluding afs panels) prime patches
  • Test document prepare and repair stage 5
  • Engage CSS to begin installation of 4th stage 
  • Engage scaffolder for levels 7 and 8 on Western side
  • Phase 2 water test on unit 103
  • Gain access to unit 810 to begin balcony prep.

In the week ahead

  • Complete render stage 5, paint stage 5

  • Complete painting stage 4 and 3 (excluding blade wall)

  • Swing stage setup, stages 6 7 and 8

  • Test, mark out, document drummy and cracked render stage 6 7 and 8

  • Begin cutting of defective render