Week commencing 23 May

  • Complete render stage 5, paint stage 5

  • Complete painting stage 4 and 3 (excluding blade wall)

  • Swing stage setup, stages 6 7 and 8

  • Test, mark out, document drummy and cracked render stage 6 7 and 8

  • Begin cutting of defective render

In the week ahead

  • Gain access to 806 to have swing stage set up 

  • Finish Stage 3 wall including paint

  • Mark out document and prep Stage 6 

  • Begin render repair to rooftop parapet and Stage 6

  • Finish Stage 5 quality check and repairs 

  • Implement forward plan and notification plan