Week commencing 30 May

  • Gain access to 806 to have swing stage set up 

  • Finish Stage 3 wall including paint

  • Mark out document and prep Stage 6 

  • Begin render repair to rooftop parapet and Stage 6

  • Finish Stage 5 quality check and repairs 

  • Implement forward plan and notification plan 

In the week ahead

  • Complete mark-out and cut-out of stages 7 and 9 

  • Complete render patching on stages 6 and 7 

  • Complete spalling repairs on blade wall 

  • Start painting on stage 6 and 7 

  • Complete mark-out and cut-out for repairs in Unit 809

  • Apply primer on current render 

  • Install glass balustrades