Week commencing 6 June

  • Complete mark-out and cut-out of stages 7 and 9 

  • Complete render patching on stages 6 and 7 

  • Complete spalling repairs on blade wall 

  • Start painting on stage 6 and 7 

  • Complete mark-out and cut-out for repairs in Unit 809

  • Apply primer on current render 

  • Install glass balustrades

In the week ahead

  • Move swingstage 3 to 8 

  • Aluminium scaffolds to Units 802 & 803

  • Painters to finish Stage 3, 4 and 5 

  • Rendering works on Stage 6, 7 and rooftop 

  • Cutting of render areas on stage 9 

  • Demolition of fencing on level 2 and roof top 

  • Organise temporary handrails, cut out parapet wall section 

  • Shift level 2 plants to eastern facade level 2 planter box after confirmation

  • Decommission courtyard lights at level 2 and rooftop 

  • Investigation for decommissioning a/c units 

  • Remove and reinstall Unit 208 bedroom door for hob 

 

** Mud plan with stages marked up coming soon. **