Week commencing 13 June

  • Move swingstage 3 to 8 

  • Aluminium scaffolds to Units 802 & 803

  • Painters to finish Stage 3, 4 and 5 

  • Rendering works on Stage 6, 7 and rooftop 

  • Cutting of render areas on stage 9 

  • Demolition of fencing on level 2 and roof top 

  • Organise temporary handrails, cut out parapet wall section 

  • Shift level 2 plants to eastern facade level 2 planter box after confirmation

  • Decommission courtyard lights at level 2 and rooftop 

  • Investigation for decommissioning a/c units 

  • Remove and reinstall Unit 208 bedroom door for hob 

In the week ahead

  • Set up road and access to next door land 

  • Set up rubbish chutes 

  • Cut out wall sections 

  • Clean general waste off Level 2 courtyards 

  • Label and move residents' plants to eastern planter box 

  • Complete temporary handrail works at eastern planter box area

  • Start demolition of courtyard pavers 

  • Stage 6, 7 and 9 render repairs

  • Stage 6 and 7 painting 

  • Stage 3 swingstage strip (access to units was cancelled last week)

  • Stage 8 swingstage install (access to units was cancelled last week)

  • Stage 1 scaffolds erecting (cancelled last week)

 

** Mud plan with stages marked up coming soon. **