Week commencing 20 June

  • Set up road and access to next door land 

  • Set up rubbish chutes 

  • Cut out wall sections 

  • Clean general waste off Level 2 courtyards 

  • Label and move residents' plants to eastern planter box 

  • Complete temporary handrail works at eastern planter box area

  • Start demolition of courtyard pavers 

  • Stage 6, 7 and 9 render repairs

  • Stage 6 and 7 painting 

  • Stage 3 swingstage strip (access to units was cancelled the earlier week)

  • Stage 8 swingstage install (access to units was cancelled the earlier week)

  • Stage 1 scaffolds erecting (cancelled the earlier week)

In the week ahead

  • Continue demolition of Level 2 

  • Continue render patch and repair Western and Southern Facade 