Week commencing 27 June

  • Demolition of Level 2 Courtyards

  • Render repairs to Stage 9

  • Finished painting stage 6 & 7

  • Mark out and break out Aluminium Stage 1 

  • Helped residents of Level 2 to clear belongings off courtyard 

In the week ahead

  • Complete demolition of Level 2 courtyard pavings 

  • Prepare area for hoist installation in front of Unit 202

  • Set up extra power boards at Level 2 and roof top 

  • Set out for courtyard fence post plinth 

  • Survey slab levels at eastern Level 2 courtyards

  • Start propping and break out brickwork for flashing repairs 

  • inspect hob detail in Unit 208

  • Strip swing stage 6 & 7 

  • Install swing stage 10 & 11

  • finish render repairs at stage 9 

  • start render repairs at Stage 8, 10, 11 and Aluminium stage 1

  • Start prime and painting stage 9 

  • Window works for Unit 806

  • Reinstall Unit 204 awnings 

   **  Please click for Mud Map of stages