Week commencing 18 July

  • Decommisioned 5 Level 2 air conditioning units, recommisioned 6 units on to wall brackets 

  • Started grinding up Level 2 membrane and installing covings

  • Started demolition of SD brick hobs, and grinding old membrane 

  • Continued removing sliding doors & temporarily framed up inside units 

  • Renderer finished Stage 8 balconies concrete corrosion spot remediation 

  • Stripped Swing stage 6, installed Stage 10

  • Installed scaffolds for hoist access onto roof terrace 

  • Bricklayer continued flashing works at Level 2 

  • Cut out parapet wall at roof terrace for hoist access

In the week ahead

  • Continue Level 2 flashing replacement 

  • Level 2 sliding doors demolition and temporary installation

  • Demolition of old brick SD hobs, form up and pour new concrete hobs

  • Complete hoist installation

  • Set up ramps and rubbish chute

  • Start demolition of roof terrace pavers

  • Continue grinding up Level 2 membrane and start coving

  • Painter to finish Aluminium Stage 1, Stage 8 balconies and start Stage 9

  • Renderer to finish Stage 9 and start Stage 10 & 11 

   **  Please click for Mud Map of stages