Week commencing 25 July

  • Hoist Installation completed

  • Safety fences and ramps installed to landings 

  • Started clearing  roof terrace of fencing, planter, rubble 

  • Level 2 of Western courtyards grinding complete and coving installed to 90%

  • 15 of Level 2 sliding doors been taken out and 10 new hobs been poured

  • Render completed on Stage 9 

  • Painter completed Stage 8 and aluminium Stage 1 

  • Flashing works completed on Western side. 

In the week ahead

  • Continue demolition of roof terrace pavings and screed

  • Strip Aluminium Stage 1 and erect Stage 2 

  • Painter to Stage 9 

  • Mark and start breaking out Stage 10 render

  • Renderer to Stage 11

  • Level 2 grinding up of old membrane to start on the Eastern side 

  • Continue removing sliding doors in Units 202, 203, 204, and 205

  • Continue to prepare and pour new door hobs 

  • Clean and pressure wash Level 2 Western courtyards ready for torch on works

  • Waterproofer to install primer and torch on membrane on Western side and start detailing new door hobs 

  • Flashing works to continue on Northern and Eastern sides

   **  Please click for Mud Map of stages