Week commencing 1 August

  • Roof terrace paving demolition - 50% completed

  • Aluminium Stage 1 stripped, Stage 2 erected

  • Level 2 cavity flashing works - 80 % completed 

  • Renderer started Stage 11 and Level 2 walls where flashing has been changed

  • Stage 10 render measured, marked and broken out

  • Stripped formwork of new SD hobs at the Western side 

  • Removed Unit 205 sliding doors 

  • Temporary remediation to Level 1 pool area leaks, removed carpet and underlay

  • Level 2 Eastern and Northern side sliding door sub sills cut to size and end caps installed

In the week ahead

  • Waterproofer to finish grinding and coving on Eastern side, pressure wash and start to install primer and membrane

  • Start grinding on Western side 

  • Painting works to Stage 9 

  • Rendering to continue on Stage 10 & 11

  • Bricklayer to finish cavity flashing works 

  • Continue demolition of roof terrace paving and screed 

  • Continue removing sliding doors on Western side, prep and pour new hobs 

  • Start installing aluminium angles on new door hobs 

  • Strip Stage 8 & 9 and install Stage 12 

   **  Please click for Mud Map of stages