Week commencing 15 August

  • Render patching completed at Aluminium Stage 2 

  • Waterproofer completed torch-on membrane at Level 2 Eastern courtyards

  • Prepped and poured new sliding door hobs at Level 2 Northern courtyards 

  • Started with 3 door hobs at the Western side

  • Aluminium termination angles installed on all Eastern courtyard hobs

  • Render patching and corrosion spot remediation on Stage 10 & 11

  • Stage 12 & 13 are installed 

  • Marked, measured and broke out corrosion spots at Stage 12 

  • Roof terrace demolition works - 90% completed

  • All Level 2 air conditioning units have been re-commissioned

In the week ahead

  • Continue render patching at Stage 10 & 11

  • Painter to complete Aluminium Stage 2, start on Stage 10

  • Change pergola fixings at Aluminium Stage 2 

  • Waterproofers to start grinding old membrane up at Level 2 Western side

  • Complete detailing around new hobs at Eastern courtyard doors

  • Mark and measure render patches at Stage 13

  • Complete roof terrace demolition, clean up and prepare for waterproofer to start

  • Start loading up materials for tile screeding 

   **  Please click for Mud Map of stages