Week commencing 25 April

  • Continue to treat underside of decking
  • Treat the top side after the installed decking has dried out and completed.
  • Waterproofing removal and WB30 Continues around Units 21 and 30. 

In the week ahead

  • Remove existing waterproofing and grind down drains in Block A
  • Treating the top side of the decking of Block B depending on the weather 
  • Putting in bearers and joists into unit 5& 6 and decking down
  • Completion of waterproofing removal around units 21 and 30.