Week commencing 26 June

  • Start painting in garage area.
  • Finish screed in unit 1 courtyard and hydropoxy.
  • Install butanol waterproofing weather dependant.
  • Install angle down side wall of unit 1 and hydropoxy slab and angle.
  • Continue with tiling of entrance ways and courtyards and grout.
  • Continue installing expansion joint to podium tiles.
  • Start installing expansion joints to courtyard tiles and entrance ways.
  • Pour footing for planter box.
  • Clean site to keep surrounding neat and tidy.

In the week ahead

  • Complete tiling works.
  • Complete installation of unit 1's courtyard wall.
  • Continue with installation of expansion joints.
  • Complete block work to planter box.
  • Complete capping tile installation.
  • Start crack stitching works.
  • Clean site to keep surrounding neat and tidy.