Week commencing 27 March

  • Continued with cavity waterproofing detail
  • Commenced waterproofing hobs for dividing walls
  • Commenced cavity flashing and brick work to cavities
  • Commenced removal of brick wall at entrance way – 6 courses down
  • Started removal and pavers and tiles at entrance way
  • Continued with spalling repair
  • Commenced core drilling for new down pipes and drainage

In the week ahead

  • Continue with cavity flashing installation and brick up 
  • Continued with excavation of entrance way and garden area 
  • Complete core hole drilling for new down pipes and drainage 
  • Start installation of pipe work for drainage and down pipes 
  • Start installation of electrical works in garage area
  • Continue with spalling repairs 
  • Remove RSJs to entrance ways and pins to walls that have been bricked up 
  • Start floor grinding to entrance ways for waterproofing 
  • Start bricking up dividing walls to courtyards (depending on weather conditions)