Week commencing 03 April

  • Continue with cavity flashing installation and brick up 
  • Continued with excavation of entrance way and garden area 
  • Complete core hole drilling for new down pipes and drainage 
  • Start installation of pipe work for drainage and down pipes 
  • Start installation of electrical works in garage area
  • Continue with spalling repairs 
  • Remove RSJs to entrance ways and pins to walls that have been bricked up 
  • Start floor grinding to entrance ways for waterproofing 
  • Start bricking up dividing walls to courtyards (depending on weather conditions)

In the week ahead

  • Continue with installation of dividing walls
  • Continue with installation of electrical cables for archway and unit number lighting
  • Continue installation of pipe work for down pipes and drainage
  • Waterproof around newly installed down pipes
  • Brick up any cavities that have been left due to new down pipes
  • Start removal of by fold doors and waterproof openings
  • Start forming levels for courtyard falls to drainage
  • Possibly start forming up entrance way slab and steps
  • Continue with spalling in unit 1's garage area
  • Start filling exposed Reo with HB40 in garage area
  • Clean site