Week commencing 10 April

  • Continue with installation of dividing walls
  • Continue with installation of electrical cables for archway and unit number lighting
  • Continue installation of pipe work for down pipes and drainage
  • Waterproof around newly installed down pipes
  • Brick up any cavities that have been left due to new down pipes
  • Start removal of by fold doors and waterproof openings
  • Start forming levels for courtyard falls to drainage
  • Possibly start forming up entrance way slab and steps
  • Continue with spalling in unit 1's garage area
  • Start filling exposed Reo with HB40 in garage area

In the week ahead

  • Continue installation of dividing walls
  • Continue installation of electrical cables for lighting to archways and above unit number's
  • Waterproof around new down pipes
  • Start finding falls to podium slab and courtyards for drainage
  • Continue with cutting out of slab for puddle flange
  • Load out brick deliveries to allocated spots for bricklayers
  • Detail entrance ways of units for waterproofing
  • Continue patching up spalling repairs
  • Start patching up spalling repairs to unit 1's garage
  • Remove step as base of kitchen door to units 3 and 4
  • Clean site