Week commencing 01 May

  • Complete screed/topping installation
  • Install Ardex WMP 300 to screed/topping
  • Remove all timber form work for drainage levels
  • Complete installation of dividing walls (except for the end of unit 1's as this is a variation)
  • Start removal of by fold doors and re-instate once waterproofing is completed
  • Complete waterproofing and installation of angle beneath doors
  • Complete spalling and HB40 works in unit 1's garage
  • Re-install unit 1's garage door
  • Complete excavation works and step removal at entrance way
  • Complete spalling/HB40 works to main garage area

In the week ahead

  • Complete screeding.
  • Complete installation of Ardex WPM 300 to screed.
  • Continue with waterproofing.
  • Continue with HB40 works to units garage and main garage area.
  • Start bricking up wall at entrance.
  • Start forming slab and stairs at entrance.
  • Possibly pour concrete slab.
  • Drill holes for conduit in podium slab.
  • Form hob around conduit and pour.
  • Clean site.