Week commencing 28 March

  • Water test of deck area to Building A 
  • Commence tile break out to units 21 to 30
  • Deliver and stack timber supplies

In the week ahead

  • Start deck on Block B timber frame and decking
  • Paint reverse side of decking
  • Carry on break out of tiles between units 21 and 30
  • Grind off waterproofing to exposed slab
  • Water test Block A slab