Week commencing 29 May

  • Complete installation of waterproofing.
  • Complete installation of pressure seal for waterproofing termination.
  • Complete water test to podium slab and courtyards.
  • Continue with installation of tiles to podium slab.
  • Start rendering balustrade hob.
  • Start installation of reo form and pour unit 1's slab.
  • Continue with HB40 works in garage area and individual garages.
  • Complete build of brick piers.
  • Check measures for balustrade.
  • Start installation of reo and form ply for entrance way and step.

In the week ahead

  • Complete water testing.
  • Continue with tiling of podium slab.
  • Start installation of expansion joint to tiles in communal area.
  • Start tiling courtyards.
  • Hydro epoxy unit 1's new slab and hob.
  • Complete screed to unit 1's courtyard.
  • Cut out slab for unit 1's drain pipe.
  • Cut out slab and repair to pressure pipe fill with blue metal and concrete.
  • Install unit 1's drain pipe in slab and infill with blue metal and concrete.
  • Continue with HB40 works in garage area.
  • Backfill pathway to podium slab ready for new slab and stairs.
  • Clean site to keep surrounding neat and tidy.