Week commencing 29 May

  • Completed fence re-installation on Roof Top and LVL2
  • Completed Sikaflex sealant application on Roof Top tile expansion joints, commenced on LVL2
  • Continued with defect repairs

In the week ahead

  • Complete Sikaflex sealant application on LVL2 tile expansion joints 
  • Complete fence lighting installation and re-connection on Roof Top and LVL2 courtyards 
  • Complete defect repairs, demobilise site office and store room