Week commencing 29 August

  • Flood test roof terraces in Unit 1, 2, 3 and 8 

  • Screed Units 2 & 3 and add waterproofing additives 

  • Render parapet cappings on Unit 3, 7 and 8 

  • Raise brickwork on Units 1, 2, and 3 to compliant height

  • Prime and paint last weeks rendered capping on Unit 4, 5, and 6 

  • Reinstate air conditioning units 1 and 3 

In the week ahead

  • Screed Units 1 and 8 

  • Waterproofing to all new screed

  • Tile works in Unit 2 and 3 roof

  • Complete all rendering works 

  • Complete Unit 4, 5, and 6 waterproofing facades

  • Remove scaffold on Unit 4, 5, and 6 

  • Strip Unit 10 staircase