Week commencing 5 September

  • Tiled roof terrace skirting in Unit 2 and 3 

  • Tiled Unit 7 small balcony 

  • Finished facade coating on Unit 4 and 5 

  • Dismantled scaffold to Unit 4 and 5 

  • Reinstate gas on parapet of Unit 4 and 5 

  • Started Unit 10 stairwell surfacing 

In the week ahead

  • Screed Units 1 and 8 

  • Prepare screeds with hydrepoxy

  • Finish Units 1, 2, 5, 6, 7, and 8 facade coatings 

  • Start internal painting

  • Prepare new balustrades 

  • Complete Unit 10 staircase 

  • Reinstate remaining gas 

  • Refit spa baths