Week commencing 12 September

  • Screed Units 1 and 8 

  • Prepare screeds with hydrepoxy

  • Finish Units 1, 2, 5, 6, 7, and 8 facade coatings 

  • Start internal painting

  • Prepare new balustrades 

  • Complete Unit 10 staircase 

  • Reinstate remaining gas 

  • Refit spa baths

In the week ahead

  • Tile Unit 1 and Unit 8 roof terraces 

  • Finish all control joints 

  • Finish coat of WB 9000 to Units 6,7, and 8 

  • Finish internal rectification painting works Unit 4 

  • Re-fit conduits in Unit 1 

  • Re-install spas in Unit 2, 3, and 7

  • Re-fit lights in Unit 1, 2, 3, 4, 5, 6, and 7

  • Water blast Units 5, 6, 7, and 8

  • Dismantle scaffolds in Units 6, 7, and 8