Week commencing 19 September

  • Final coat of WB9000 to Units 6, 7, and 8 

  • Reinstalled spa in Unit 7

  • Unit 8 roof terrace floor tiles complete

  • Lights re-fitted in Units 1, 2, 3, 4, 5, 6, and 7

  • Unit 5, 6, 7 , and 8 water blasting completed

  • Scaffold dismantled around Units 6, 7, and 8 

  • Control joints near completion 

In the week ahead

  • Grout in Unit 8 floor tiles

  • Unit 2, 3, and 8 skirting tiles

  • Tile Unit 7 parapet wall mosaic

  • Screed and tile Unit 1 roof terrace

  • Finish all control joints

  • Final coat of WB9000 to Units 1, 2, and 3

  • Start to dismantle scaffolds in Unit 1, 2, and 3

  • Re-install spas in Unit 2 and 3

  • Complete internal paintings in Unit 1 and 4