Week commencing 26 September

  • Spas reinstalled in Unit 2 and 3 

  • Skirting tiles in Unit 2, 3, and 8 completed 

  • Control joints completed 

  • Final coat of WB9000 to Units 1, 2, and 3 facade 

  • Unit 6 & 8 bathroom demolition works completed 

  • Unit 6 & 8 bathroom render works completed 

  • Unit 7 mosaic tiles near completion 

  • New balustrades installed to Unit 3 and 8 roof terrace 

In the week ahead

  • Screed Unit 2 

  • Dismantle scaffold Unit 1 and 2 

  • Complete bathroom membranes in Unit 6 & 8 

  • Grout Unit 8 roof tiles 

  • Grout remaining small balcony tiles 

  • Install balustrade in Unit 2 

  • Water test Unit 1 roof terrace 

  • Complete Unit 7 mosaic and hob tiles 

  • Re-fit boilers Unit 1 & 7