Week commencing 4 October 

  • Unit 2 horning screed finished 

  • Unit 6 & 8 membrane in bathrooms completed 

  • Unit 2 & 3 small balcony tiles grouted 

  • Unit 8 roof tiles grouted 

  • Boilers re-fitted to Unit 1 & 7 

  • Scaffold dismantled from Unit 2 & 3 

In the week ahead

  • Install balustrade in Unit 2 & 10 

  • Screed Unit 1 (pending water test)

  • Finish Unit 7 mosaic and hob tiles (awaiting tiles)

  • Extend Unit 8 parapet wall

  • Water blasting in Unit 2 & 3 

  • Sika application to all skirting tiles and tile edges

  • Sika application to all floor tile control joints 

  • Render Unit 5 internal hob